Bear Valley Road Construction Update, November 13

A road runs through a dry landscape with power poles, hills in the background, and a vehicle driving on it.

Work is continuing on the Bear Valley Road Rehabilitation Project. Last week, crews completed paving on the first section of the project.


Today (November 13), crews are installing underground water pipes between Martingale Way and Hart Drive. Crews will also pressure-test the water line between the Frontage Roads.


Next week's construction schedule will depend on weather conditions. At this time, work is expected to be on hold for the week, although that could change. The CSD will provide additional updates if work is added to next week's schedule.


Crews are scheduled to pave a short section of the road on November 23, weather permitting. The CSD has spoken with the contractor to ensure this work is completed before Thanksgiving, and that both lanes of Bear Valley Road will be open by November 26.


The CSD is working closely with the contractor and construction manager to plan the remaining phases of the project. With winter weather approaching, we do not anticipate scheduling additional paving until 2027. Water line work will continue as weather permits.


This $9.4 million project is funded through both the CSD Roads Assessment and Water Fees because it includes water line replacement and roadway improvements.


Thank you again for your patience, and please continue to drive safely through construction zones.