Community Services District Project Updates

Bear Valley Road Rehabilitation Project
The Bear Valley Road Rehabilitation Project will include a complete reconstruction of Bear Valley Road from the gate to Oakflat Drive, and from Bay Court to Martingale Way. Water main lines and service lines will also be replaced as part of the project.
The current estimate for the project is $9.3 Million. The road replacement portion will be funded from the Roads Fund, and the water line replacement portion will be funded from the Water Enterprise Fund.
When construction begins, please expect delays on our roads. The CSD will utilize Nixle, the Electronic Gate Marquee, the CSD Website, and Social Media to send timely alerts on road closures.
- April 16, 2026 - Engineering firm Provost and Pritchard approaches 65% completion mark on design work
- December 17, 2025 - CSD Board of Directors Authorizes Agreement with engineering firm Provost and Pritchard to begin design work on Bear Valley Road Rehabilitation Project
- September 11, 2025 - CSD Board of Directors receives Bear Valley Road Rehabilitation Project Engineering Study, examining several options to determine the best and most cost-effective method for rehabilitation
- December 12, 2024 - CSD Board of Directors Approves Engineering Study for Bear Valley Road Rehabilitation

Oakflat Booster Station Project
Pavement Management Project